Supply desk · Updated October 2026

GPU server availability and lead times.

What you can order today, how long it takes, and what’s closed. Lead times are ex-works, from published market reports, before shipping to India.

Supply status by GPU

GPUStatusLead timeNotes
NVIDIA B300 (Blackwell Ultra)Allocation8–20 weeksShipping since January 2026. Supply tight through Q3 2026.
NVIDIA GB300 NVL72AllocationLonger than 8-GPU serversRack-scale and fully liquid-cooled. Planned with the facility from day one.
NVIDIA GB200 NVL72AllocationLonger than 8-GPU serversSold out through mid-2026 per market reports. GB300 NVL72 is its successor.
NVIDIA B200Allocation8–16 weeks with an OEM allocation; 30+ withoutAllocation-gated. Who you buy through decides the wait.
NVIDIA H200Shipping2–4 weeksThe quickest Hopper-class server to buy today.
NVIDIA H100Orders closedNot orderableNVIDIA is no longer taking new orders. H100 NVL last-time-buy closed 1 Nov 2025.
NVIDIA RTX PRO 6000 BlackwellShippingQuoted per orderSuccessor to the L40S for PCIe servers.
NVIDIA L40SShippingQuoted per orderStill in production; no end-of-life notice. The older L40 has reached end of life.
AMD Instinct MI300XShippingQuoted per orderMI355X now generally available; MI400 announced for 2026.

What it means for buyers in India

Need GPUs this quarter?
H200 is the fastest Hopper-class server to buy. Blackwell depends on allocation.
Planning Blackwell?
Order through a partner with an OEM allocation. Without one, B200 waits run past 30 weeks.
Own H100s?
New H100 orders are closed, so existing servers hold their value. Host them, lease out idle time, or sell.
India timing
Add shipping, customs clearance and racking to any lead time. We plan all three with the order.
Server shipping crates at a data-centre receiving bay.

Delivery

Lead time ends at the rack, not the factory.

We plan the import, the receiving bay and the rack with the order, so the server goes live the week it lands.

How delivery works

Questions

What is the B200 lead time in 2026?

About 8–16 weeks for buyers with an OEM allocation, and 30 weeks or more without one, based on May 2026 market reports.

Can I still buy NVIDIA H100 servers?

No. NVIDIA is no longer taking new H100 orders. H200 is the current Hopper option.

Which GPU server can I get fastest?

H200 servers, at around 2–4 weeks from the OEM in mid-2026, plus shipping and import to India.

Is B300 shipping?

Yes. NVIDIA began shipping B300 (Blackwell Ultra) systems in January 2026, with supply tight through Q3 2026.